Regional hospital expansion recovered from nine-month delay.
Problem
A $220M hospital expansion was nine months behind schedule and trending $18M over budget, with deteriorating relationships between the owner, GC and design team.
Strategy
Anthart embedded a recovery advisory team, restructured the project governance, reset the schedule baseline and re-sequenced critical-path activities.
Outcome
- Returned to schedule within 90 days
- 11% recovery of projected cost overrun
- New owner-rep governance retained post-recovery